DATEDESCRIPTION
02/17/2000 Order Initiating Testing, Assigning Project Leader and Calling for Proposed Master Test Plan and Performance Standards to be Developed by KPMG Peat Marwick
03/29/2000 Bell Atlantic OSS Evaluation Project Master Test Plan (Draft Version 1.0)
03/31/2000 Project Leader Ruling Seeking Comments on Master Test Plan
04/27/2000 Virginia Carrier to Carrier Guidelines Performance Standards and Results (Consolidated Test Metrics Draft) - Please see appendices and exhibits associated with this document by accessing OSS Appendices/Exhibits
04/28/2000 Project Leader Ruling Seeking Comments on Metrics
05/31/2000 Project Leader Ruling Adopting Master Test Plan
05/31/2000 Bell Atlantic OSS Evaluation Project Master Test Plan (Final Release Version 1.0)
08/11/2000 Project Leader Ruling Adopting Metrics
08/11/2000 Virginia Carrier to Carrier Guidelines Performance Standards and Results (Final Clean Version) - Please see appendices and exhibits associated with this document by accessing OSS Appendices/Exhibits
10/02/2000 Project Leader Ruling Seeking Comments On Verizon's Requested Modification To The Master Test Plan - Please see appendices and exhibits associated with this document by accessing OSS Appendices/Exhibits
11/28/2000 Bell Atlantic OSS Evaluation Project Master Test Plan (Final Release Version 1.1)
11/29/2000 Project Leader Ruling Adopting Protective Agreement
12/07/2000 Virginia OSS Test Schedule (Original)
02/06/2001 Verizon's Letter Concerning Test Schedule Delay
02/09/2001 AT&T's Petition to Add Line Splitting to the MTP
02/12/2001 KPMG's Comparability Study of Verizon's Maryland, District of Columbia, Virginia, and West Virginia OSS, Version 1.0.
02/13/2001 First Revised Virginia OSS Test Schedule
02/14/2001 Project Leader Ruling Seeking Comments on AT&T's Request to Add Line Splitting to the Master Test Plan
02/16/2001 Verizon's Request Regarding OR-10
03/05/2001 Project Leader Ruling Seeking Comments on Verizon's Request Regarding Metric OR-10
04/06/2001 Project Leader Ruling on Adding Line Splitting to the Master Test Plan
04/27/2001 Project Leader Ruling Regarding Metric OR-10
05/30/2001 Schedule Change - Metrics Replication
06/13/2001 AT&T's Petition Regarding Electronic Wholesale Bills
06/19/2001 Project Leader Ruling Seeking Comments on AT&T's Request to Clarify or Amend the Master Test Plan Regarding Electronic Billing
06/22/2001 Second Revised OSS Test Schedule
07/10/2001 Third OSS Test Schedule
08/10/2001 Project Leader Ruling on AT&T's Request to Clarify or Amend The Master Test Plan Regarding Electronic Billing
11/09/2001 Fourth Revised OSS Test Schedule
11/30/2001 Project Leader Ruling on Adding Line Splitting to the Master Test Plan
03/04/2002 Project Leader Ruling for Notice of KPMG's Draft Report and Scheduling Workshops
03/20/2002 Preliminary Order on Verizon Virginia Inc.'s Compliance with the Conditions Set Forth in Section 271(C) of the Telecommunications Act of 1996 and Order Amending Reporting Requirements on Third-Party Testing of Operation Support Systems
04/16/2002 Project Leader Ruling for Notice of KPMG's Final Report
11/06/2002 Order Closing Cases